Foundations and special underground works
1290 – The Cityringen Metro Project – Copenhagen (Denmark)
Works:
Execution of drilling and grouting works at the Frederiksberg station for the TBM breakthrough.
Buyer:
CMT - Copenhagen Metro Team
Period of Execution:
January 2013 - December 2014
Works Amount:
€ 23.742.148,00
Importo lavori Frederiksberg
€ 1.245.143,00
Description
Bored piles D114 were executed in order to properly consolidate the soil where two TBMs would break through. Installation of piles for a total length exciding 10.000 m in different distinct areas, working both above- and underground.